Lead Times by Brand

These are factory production lead times. We do not account for the shop drawing approval process, and shipping times from the factory to the jobsite. We highly encourage you to review your project early as price increases are erratic and no longer on an annual cycle.

Last Updated: March 2nd, 2023.

Andersen

  • E-Series: 15-17 weeks
  • A-Series: 11-13 weeks
  • 100 Series: 3-5 weeks, 5-7 weeks (Shapes), 4-6 weeks (Mulled Units)
  • 200 Series: 2-4 weeks
  • 400 Series: 2-4 weeks (DH, Fixed), 7-9 weeks (Casement), 3-5 weeks (Glider)

Fleetwood

  • Any Series Custom Finish: 30 weeks
  • 3000 Series Standard Finish: 16 weeks
  • 3200: 16 weeks, 3600: 16 weeks, 3900: 16 weeks, 4400: 16 weeks Series Standard Finish
  • 3050: 16 weeks, 3070: 16 weeks, 4070: 16 weeks, EDGE Doors Series: 16 weeks Standard Finish
  • 330: 16 weeks, 3800 Series: 16 weeks Standard Finish
  • 350 Series: 16 weeks and 450 Series: 16 weeks

Jeld-Wen

  • Siteline: 11 weeks
  • Custom: 10 weeks
  • Vinyl: 4 weeks
  • IWP & Aurora: 6-8 weeks

Marvin

  • Ultimate: 18-19 weeks (Windows), 10-11 weeks (Doors), 24-25 weeks (Shapes/Mulls)
  • Modern: 19-20 weeks
  • Elevate: 11-13 weeks
  • Essential: 6-7 weeks, 8-9 weeks (Shapes/Mulls)

LaCantina Doors

  • Bifolds: 4 weeks, 8 weeks (Custom), 12 weeks (V2 Alum Int), 24 weeks (V2 Wood Int)
  • Pivot/Swing Doors: 13 weeks
  • Multislides: 14 weeks

Milgard

  • Trinsic: 3-4 weeks
  • Tuscany: 3-4 weeks
  • Style Line: 2-3 weeks
  • Casements: 3-4 weeks
  • Sliding Doors: 3-4 weeks
  • Swing Doors: 2-3 weeks

TruStile

  • Modified Daily. Spontaneous variability over 1 month. 2-8 weeks average MDF.

Euroline

  • CAD Drawing: 6-8 weeks
  • Production: 30-42 weeks after CADs Approval
  • Drafting Revisions: 4-6 weeks